Data Type    Integer List

Entry Type    Entered

Description    The Unique ID Predecessors field lists the unique ID numbers for the predecessor tasks on which a task depends before it can be started or finished. Each predecessor is linked to the task by a specific type of task dependency and a lead time or lag time.

Best Uses    Add the Unique ID Predecessors field to a task view when you want to display or update task predecessors as identified by their unique IDs rather than task IDs. Each predecessor is represented by its unique ID number, which may be followed by a dependency and the lead or lag time. The dependency types for predecessors are FS (finish-to-start), FF (finish-to-finish), SS (start-to-start), and SF (start-to-finish). To enter lead time, type a negative number. To enter lag time, type a positive number.

Example    You want to review the predecessors of tasks in your project to analyze and refine the schedule. You add the Unique ID field and the Unique ID Predecessors field to the Task Sheet view. In the Predecessors field for the "Write proposal" task, you see the entry "14FS+3d." This means that the task with Unique ID14 is a predecessor of this task, with a finish-to-start dependency and a 3-day lag time. Before this task can start, it must wait 3 days after the finish of the task with Unique ID14. The Unique ID Predecessors field for the "Conduct client meetings" task is blank. You type "15FS" to link this task to the task with Unique ID15 with a finish-to-start dependency.

Remarks    If you enter only the task unique ID number in the Unique ID Predecessors field, Project assumes a finish-to-start dependency with zero lag time. If there is more than one predecessor, they are all listed and separated by the list-separator character, which is typically the comma.

You can use the Link Tasks command on the Edit menu to link the selected tasks with finish-to-start dependencies and zero lag time. You can also link tasks by dragging from one task to the other on the chart portion of the Gantt Chart or Network Diagram.

If a predecessor is a task in another project, the Unique ID Predecessors field also contains the path to the linked project, in addition to the task Unique ID and dependency type. An example is: C:\My Documents\Bldg E Construction.mpp\3FF.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×