Masuk dengan Microsoft
Masuk atau buat akun.
Halo,
Pilih akun lain.
Anda memiliki beberapa akun
Pilih akun yang ingin Anda gunakan untuk masuk.
Bahasa Inggris
Maaf. Artikel ini tidak tersedia dalam bahasa Anda.

Data Type    Duration

Entry Type    Calculated or entered

Description    The Actual Duration field shows the span of actual working time for a task so far, based on the scheduled duration and current remaining work or percent complete.

How Calculated    If you type a value in the % Complete field, Project calculates actual duration as follows:

Actual Duration = Duration * Percent Complete

If you type a value in the Actual Duration field, Project calculates the Remaining Duration as follows:

Remaining Duration = Duration - Actual Duration

If you enter an actual duration greater than the scheduled duration, Project changes scheduled duration to match the new actual duration, sets the remaining duration to zero, and sets the percent complete to 100.

Best Uses    Add the Actual Duration field to a task sheet when you want to view, filter, or edit actual duration for tasks. If you edit this field, however, the remaining duration and percent complete fields are recalculated.

Example    The scheduled duration for the "Conduct client meetings" task is 3 days. If the task is 33 percent complete, the actual duration is 1 day.

Remarks    Because entering a value in the Actual Duration, Remaining Duration, or % Complete field automatically recalculates the other fields, you should enter a value in only one of these fields for a task.

Editing remaining duration affects total scheduled duration rather than actual duration.

When you enter percent complete or total actual work, Project reschedules remaining work around the status date by default. If you prefer, you can leave these tracking fields in the project as originally scheduled, even if completed work is shown in the future or remaining work is shown in the past. You can turn off these settings in the Project Options dialog box.

To set the status date to a date other than today's date, open the Project Information dialog box.

Perlu bantuan lainnya?

Ingin opsi lainnya?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Apakah informasi ini berguna?

Apa yang memengaruhi pengalaman Anda?
Dengan menekan kirim, umpan balik Anda akan digunakan untuk meningkatkan produk dan layanan Microsoft. Admin TI Anda akan dapat mengumpulkan data ini. Pernyataan Privasi.

Terima kasih atas umpan balik Anda!

×